This is the final week and we have finished our stage and dome project. This past week we had to finish connecting the struts to ...
Read moreThese two weeks we attached walls on to the stage by nailing them down, to make it stronger and more stable so the wind wouldn't ...
Read moreWe started to sort out the struts and hubs for the dome. Originally the hubs were smaller than they are now, the reason we had ...
Read moreWe got our music class at school to test our sound dome and stage. They did a small performance, here it is.... Here is Atama ...
Read moreThese two weeks we finished off placing the ply wood then screwing it down. We had to saw off any over hanging pieces of plywood, ...
Read moreWe decided to go with the advice our adviser Greg Kelly gave us about laminating an arch to provide support for the rest of the ...
Read moreThese weeks we nailed the joists on to the bearers and sawed off the extra overhanging wood on the sides. Some of the joists are ...
Read moreThe geodesic dome sound shell plans we originally had weren't that great, so Shontae found this 3D model on sketch-up 3D warehouse. We had to ...
Read moreThese two weeks we have finished digging the pile holes and concreted them. We also drilled holes through the bearers and piles to put the ...
Read moreKrystal put a post on the offical ngaruawahia high facebook page to see if anyone had any old fence battens or post to donate for ...
Read moreIf you're considering a career in building and construction, create a BCITO work profile. We'll do our best to get you an apprenticeship when you're finished school.